吊装 Hoisting
◎根据设计要求,采用右图不同的吊装方式;
◎根据随附标签指示,将产品吊装至正确位置。吊装过程保持
平衡;
◎严禁采用三角或两角吊点进行吊装,以免受力失衡而发生侧翻或脱吊现象;
◎产品吊装就位后,及时将顶部防雨塑料罩取下,以防因电焊等作业引起燃烧。
The according to the design requirements, different ways of using the lifting@According to the attached label instructions, product lifting to the correctposition.The hoisting process of balance;Prohibited the use of triangular or two lifting point lifting force, in order toavoid the imbalance and rollover or hanging off phenomenon;Product lifting, timely rain will be at the top of the plastic cover removed.to prevent burning caused by welding and other operations.
就位 安装In place Installation
◎单元就位后,将地脚螺钉拧进脚支撑内,调节个别螺钉,使单元完全与甲板平稳接触,最后将地脚螺钉与甲板焊接牢固;
◎全船进行管路系统压力试压前,务必将单元进水球阀关闭,避免瞬间压力过大而损坏单元管路系统及精密卫浴配件;
◎卫生单元管系试验压力范围:0.6~0.8Mpa。Unit in place,The anchor bolt screwed into the foot support,Individual adjustment screw,The unit is completely smooth contactwith the deck,At the end of the anchor bolt and the deck welding firm;OThe whole ship for pressure piping system pressure test,Make surethe unit inlet valve closed,Avoid excessive damage to units ofinstantaneous pressure pipeline system and the precision of bathroomaccessories;
Health unit piping pressure testrange:0.6~0.8Mpa.